Description

Based on the proposed scope, the skills analysis, and the reports from previous projects, make an estimate of the required resources to complete the project within the anticipated delivery date.

Roles

ResponsibleProject Manager
AccountableProject Manager
ConsultedAny
InformedAll

Steps

  1. Estimate Project Resources:

    Use previous project reports, the proposed project scope, and the required skills analysis to make an estimate of the team size calling out any specialist skills required.
  2. Estimate the Facilities Needed:

    Estimate the facilities needed to house the project team and conduct the project work.
  3. Estimate Equipment:

    Estimate any specialist equipment over and above the standard office equipment provided for knowledge workers. For example test equipment and staging environments.