Activity - Plan Iteration Resources

Activity Information

Plan Iteration Resources

Description

Based on the proposed iteration backlog, the skills analysis, and the reports from previous iterations, make an estimate of the required resources to complete the iteration within the anticipated schedule.

Attributes

Element Categories[CMMI Level 2] PP SP 2.4, [CMMI Cycle 4] Iteration, [CMMI Track 3] Build, [CMMI Track 4] Stabilize
Entry Criteria

Proposed Iteration Backlog:
The proposed list of tasks of the iteration.

Previous Iteration Reports:
Project reports from previous iterations.

Skills Analysis:
A list of the required skills to complete the iteration.

Stakeholder Involvement Plan:
A plan describing the required involvement of stakeholders to complete the iteration.

Exit Criteria

Iteration Resource Request:
A list of the required resources that may also include named individuals.

Is RequiredYes

Steps

  1. Estimate Iteration Resources:

    Use the previous iteration reports, the proposed iteration backlog, and the required skills analysis to make an estimate of the team size naming any specific individuals with specialist required skills.

Successors

TypeNameDependency Type
Form Iteration Team(s)Finish-Start