Activity Information Monitor Risks
DescriptionOn a daily basis, monitor mitigation actions for completion, risk triggers, and risk materialization. Report risk status. StepsAnalyze Metrics and Trigger Data:
Examine project metrics, reports, and project management tracking for risk trigger information. Select Risks for Mitigation Action:
If a risk mitigation has been triggered from input metrics and data, then change its state to active and move it to the Plan Mitigation activity. Select Risks for Contingency Action:
If a risk has materialized and an occurrence is observed, authorize contingency action. Create the tasks described in the contingency plan, and assign them to individuals. Report Risk Status:
Report an update on all risk status including current risk mitigation actions, metrics on risk triggers, and any contingency recovery actions underway.
Inputs and Outputs| WorkProduct | Input | Output | Allowable States |
|---|
| Risk |  |  | Active |
|
Last modified at 12/19/2007 10:37 AM by Administrator
|
|