Activity - Define Project Roles and Responsibilities

Activity Information

Define Project Roles and Responsibilities

Description

Once a team has been defined for a project, team members should be assigned roles and responsibilities. Particular attention should be paid to team members responsible for communication between sub-teams or shared functional resources.

Attributes

Element Categories[CMMI Track 2] Planning, [CMMI Level 3] IT SP 2.3, [CMMI Level 3] IPM SP 4.1, [CMMI Cycle 5] Project
Entry Criteria

Project Team and Organization Chart:
An organization chart and a list of available team members.

Exit Criteria

Updated Organization Chart:
An updated organization chart with roles and responsibilities assigned against all individuals.

Is RequiredYes

Steps

  1. Assign Roles:

    Assign a role from the set available in the process guidance to each team member or functional staff resource assigned to the project.
  2. Assign Responsibilities:

    Assign team members into spots on the organization chart.

Predecessors

TypeNameDependency Type
Establish Project Team CharterFinish-Start

Successors

TypeNameDependency Type
Define Communication PlanFinish-Start