Activity - Define Iteration Budget and Schedule

Activity Information

Define Iteration Budget and Schedule

Description

Based on the estimate for the iteration and resource plans, define the budget and schedule and publish them to the project portal.

Roles

ResponsibleProject Manager
AccountableProject Manager
ConsultedAny
InformedAll

Attributes

Element Categories[CMMI Level 2] PP SP 2.1, [CMMI Cycle 4] Iteration, [CMMI Track 3] Build, [CMMI Report 16] Unplanned Work, [CMMI Report 07] Reactivations, [CMMI Track 4] Stabilize
Entry Criteria

Proposed Iteration Backlog:
The proposed work item backlog for the iteration.

Iteration Resource Request:
A request for staffing, facilities, and equipment to complete the iteration.

Exit Criteria

Budget and Schedule:
An iteration financial budget request and proposed completion date.

Is RequiredYes

Steps

  1. Define Detailed Schedule for Iteration (Optional):

    If desired, export the work items to Microsoft Project, and define a detailed schedule of work item dependencies.
  2. Define End Date for Iteration:

    Define the end date. Usually this will be based on the steady rhythm of the iteration length determined for the project as a whole.

    If there is reason to adjust the normal iteration length, then do so and clearly communicate why there is a change in length and whether this is a single occurrence or a change to be reflected in all future project iterations.

    Adjust the proposed iteration backlog based on any changes to the iteration length.
  3. Define Budget for the Iteration:

    Determine the budget based on the resource, facilities, and equipment required against the length of the iteration. Buffer the budget estimate for contingency costs in the risk plan and provide some slack time to facilitate corrective action and issue resolution, if required.
  4. Publish Estimate and Budget:

    Publish the budget and scheduled iteration completion date to the project portal.

Predecessors

TypeNameDependency Type
Estimate IterationFinish-Start

Successors

TypeNameDependency Type
Iteration Plan ReviewFinish-Start